County Road 48 (Ontario Street/Quebec Street/George Street W/George Street E) - Road Reconstruction

Share County Road 48 (Ontario Street/Quebec Street/George Street W/George Street E) - Road Reconstruction on Facebook Share County Road 48 (Ontario Street/Quebec Street/George Street W/George Street E) - Road Reconstruction on Twitter Share County Road 48 (Ontario Street/Quebec Street/George Street W/George Street E) - Road Reconstruction on Linkedin Email County Road 48 (Ontario Street/Quebec Street/George Street W/George Street E) - Road Reconstruction link

Peterborough County and Havelock-Belmont-Methuen have partnered on the reconstruction of County Road 48 (George St.) in Havelock. Given the extensive scope of the project, the work has been divided into three (3) phases, including several sub-phases.

Construction Update:

In 2025, the following sub-phases were completed:

  • Phase 1b – George Street East, from Victoria Street to Oak Street
  • Phase 1d – Quebec Street, from Ottawa Street (Hwy 7) to George Street West

In 2026, construction on Phase 1C - from Quebec Street to Oak Street will begin in May and continue until July.

Scope of Work:

  • Replacement of buried infrastructure (ex., water main, stormwater network, and sanitary system).
  • Replacement of concrete sidewalks
  • Replacement of the asphalt roadway surface

Key Points:

  • Staged road closures will be required
  • Pedestrian access will be maintained
  • Businesses will remain open, with alternative parking arrangements provided.
  • Access for emergency vehicles will be available at all times

We appreciate everyone's patience and cooperation as we work to improve local infrastructure. For ongoing updates and detour information, please visit: Municipal511

Peterborough County and Havelock-Belmont-Methuen have partnered on the reconstruction of County Road 48 (George St.) in Havelock. Given the extensive scope of the project, the work has been divided into three (3) phases, including several sub-phases.

Construction Update:

In 2025, the following sub-phases were completed:

  • Phase 1b – George Street East, from Victoria Street to Oak Street
  • Phase 1d – Quebec Street, from Ottawa Street (Hwy 7) to George Street West

In 2026, construction on Phase 1C - from Quebec Street to Oak Street will begin in May and continue until July.

Scope of Work:

  • Replacement of buried infrastructure (ex., water main, stormwater network, and sanitary system).
  • Replacement of concrete sidewalks
  • Replacement of the asphalt roadway surface

Key Points:

  • Staged road closures will be required
  • Pedestrian access will be maintained
  • Businesses will remain open, with alternative parking arrangements provided.
  • Access for emergency vehicles will be available at all times

We appreciate everyone's patience and cooperation as we work to improve local infrastructure. For ongoing updates and detour information, please visit: Municipal511

Page last updated: 02 Dec 2025, 09:00 AM