Share CR 22 (Curve Lake Rd/16th Line) and CR 23 (Buckhorn Road) - Road Reconstruction & Intersection Enhancements on FacebookShare CR 22 (Curve Lake Rd/16th Line) and CR 23 (Buckhorn Road) - Road Reconstruction & Intersection Enhancements on X (formerly Twitter)Share CR 22 (Curve Lake Rd/16th Line) and CR 23 (Buckhorn Road) - Road Reconstruction & Intersection Enhancements on LinkedinEmail CR 22 (Curve Lake Rd/16th Line) and CR 23 (Buckhorn Road) - Road Reconstruction & Intersection Enhancements link
Peterborough County has undertaken a Municipal Class Environmental Assessment (MCEA) Study to complete intersection enhancements at County Road 22 (Curve Lake Road/16th Line) and County Road 23 (Buckhorn Road ).
The general location of the Study is shown in the figure below.
Study Purpose
Traffic congestion on Buckhorn Road during peak traffic periods has increased to a level that has triggered Peterborough County to study the issue and determine a plan to help address the problem.
Project Objective
The study identifies and evaluates potential improvements to address traffic congestion, increase safety, and accommodate future traffic conditions.
Municipal Class Environmental Assessment
This project has been completed following the Municipal Class Environmental Assessment framework. The project has been classified as a Schedule B and includes 3 phases:
Phase 1: Identifying the Problem and Objectives
Phase 2: Evaluate Alternative Solutions and Select Preferred Solution
Phase 3: Project File Report, Detailed Design, and Implementation
For a full description of the Municipal Class Environmental Assessment process that was followed for this project, please see the links under “Documents” on the right side of this page.
Construction Phase
The MCEA recommended a full road and intersection reconstruction with new left- and right-turn lanes and new traffic signal lights. Construction is commencing in July 2026.
Peterborough County has undertaken a Municipal Class Environmental Assessment (MCEA) Study to complete intersection enhancements at County Road 22 (Curve Lake Road/16th Line) and County Road 23 (Buckhorn Road ).
The general location of the Study is shown in the figure below.
Study Purpose
Traffic congestion on Buckhorn Road during peak traffic periods has increased to a level that has triggered Peterborough County to study the issue and determine a plan to help address the problem.
Project Objective
The study identifies and evaluates potential improvements to address traffic congestion, increase safety, and accommodate future traffic conditions.
Municipal Class Environmental Assessment
This project has been completed following the Municipal Class Environmental Assessment framework. The project has been classified as a Schedule B and includes 3 phases:
Phase 1: Identifying the Problem and Objectives
Phase 2: Evaluate Alternative Solutions and Select Preferred Solution
Phase 3: Project File Report, Detailed Design, and Implementation
For a full description of the Municipal Class Environmental Assessment process that was followed for this project, please see the links under “Documents” on the right side of this page.
Construction Phase
The MCEA recommended a full road and intersection reconstruction with new left- and right-turn lanes and new traffic signal lights. Construction is commencing in July 2026.
Share When does the construction start? Will this intersection be closed or still allow for traffic to move through on FacebookShare When does the construction start? Will this intersection be closed or still allow for traffic to move through on X (formerly Twitter)Share When does the construction start? Will this intersection be closed or still allow for traffic to move through on LinkedinEmail When does the construction start? Will this intersection be closed or still allow for traffic to move through link
When does the construction start? Will this intersection be closed or still allow for traffic to move through
Rebekah
asked
about 1 month ago
Construction is anticipated to start the week of July 20th, 2026. The intersection will remain open during construction, with single-lane restrictions and flagging operations in place as needed. Please anticipate delays when travelling in the area.
Share Will there be an advanced green for those going north and wanting to turn left to go to Curve Lake? on FacebookShare Will there be an advanced green for those going north and wanting to turn left to go to Curve Lake? on X (formerly Twitter)Share Will there be an advanced green for those going north and wanting to turn left to go to Curve Lake? on LinkedinEmail Will there be an advanced green for those going north and wanting to turn left to go to Curve Lake? link
Will there be an advanced green for those going north and wanting to turn left to go to Curve Lake?
27 days ago
Yes, there will be an advanced green for those going north and wanting to turn left to go to Curve Lake.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends